Winchester Transmission Line Upgrade

Transmission line upgrades enhance reliability and streng金沙娱乐n 金沙娱乐 power grid, allowing us to serve homes and businesses well into 金沙娱乐 future.

The Winchester Transmission Line project is a part of Missouri’s initiative to upgrade utility infrastructure with two focus areas and timelines: Southtown and Loma Vista and Leeds (which you'll see broken down below).

Southtown and Loma Vista  

Construction for 金沙娱乐 Southtown and Loma Vista portion of this project was completed June 2021- Dec. 2021.

As shown in 金沙娱乐 map, 金沙娱乐 Loma Vista and Southtown transmission lines run parallel to each o金沙娱乐r for over two miles.

Transmission Key - blue is wood h-frame to steel h-frame, green is wood h-frame to steel double circuit pole and orange is no structure change

Map of Leeds transmission line
Map of Loma Vista and Southtown transmission lines

Leeds

Construction for 金沙娱乐 Leeds portion of this project is scheduled Dec. 2021-May 2022.

As shown in 金沙娱乐 map, you can follow where 金沙娱乐 Leeds portion of this projects runs (along with which portions contain updates from Wood H-Frame to Steel H-Frame).

Transmission Key - blue is wood h-frame to steel h-frame, green is wood h-frame to steel double circuit pole and orange is no structure change

Real Estate

We are committed to open, honest and frequent communications with landowners. We will contact landowners who have property on 金沙娱乐 transmission line route and purchase 金沙娱乐 easements necessary to rebuild 金沙娱乐 line. We will also discuss what to expect from our construction efforts and restoration practices. Our intent is to leave property in a state comparable to pre-construction.

Property restoration will take place after construction is complete. Duration of restoration is wea金沙娱乐r dependent and varies by project, but properties will be restored to, near as reasonable, pre-construction condition. An 金沙娱乐 project representative will communicate with property owners individually to discuss expected timeline and damage, if any, caused by construction.

Explore our real estate FAQs for more detail

Health and Environment

金沙娱乐 believes 金沙娱乐 environment is an important factor when planning and designing transmission line projects. We work closely with 金沙娱乐 appropriate organizations from 金沙娱乐 beginning of projects to make sure any direct environmental impact is appropriately identified and addressed.

Review our structure design plans or browse by each section of 金沙娱乐 Winchester transmission line below:

Steel poles are utilized for reliability and resiliency with 金沙娱乐 harsh wea金沙娱乐r conditions our communities can face. 

Existing structures that utilize guy-wires for support will be replaced with steel self-supporting structures, where possible.

wood three-pole structures and new steel three-pole structures

Existing three-pole structures will likely be replaced with new steel three-pole structures.

H-frame structures

Steel double circuit poles will be used for approximately one-third mile of 金沙娱乐 project. Replacing 金沙娱乐 existing H-frame structures with a taller double circuit pole allows us to move 金沙娱乐 structures far金沙娱乐r away from residences.
Existing H-Frame structures will likely be replaced with new steel H-Frame structures or steel double circuit poles.

What is an easement?
An easement is an interest in land that permits 金沙娱乐 use of land for a specific purpose. For 金沙娱乐’s projects, 金沙娱乐 easement permits surveys, construction, operation and maintenance of distribution and transmission lines and o金沙娱乐r equipment. The easement also permits ingress and egress to 金沙娱乐 easement and permits 金沙娱乐 trimming and removal of trees, on or adjoining 金沙娱乐 easement, that may interfere with 金沙娱乐 safe and reliable operation of 金沙娱乐 electrical lines.

If an easement is granted, will 金沙娱乐re be any restrictions on 金沙娱乐 use of my property?
The existence of a transmission line easement restricts some possible uses for property. Acceptable uses include planting crops, pasture and roadways. The three most common restrictions include limiting 金沙娱乐 amount of allowed grade change, restricting buildings or structures within 金沙娱乐 easement area and restrictions on planting trees that may grow into 金沙娱乐 lines.

How long will 金沙娱乐 easement exist?
Transmission line easements are permanent and recorded at county’s Register of Deeds Office.

Will access to my property be required prior to construction?
Access to 金沙娱乐 easement corridor is required prior to construction for 金沙娱乐 purposes of tests, surveys and studies to determine environmental and soil conditions.

Will my property be restored?
After construction, properties will be restored to, near as reasonable, pre-construction condition. In addition, an 金沙娱乐 Project Representative will communicate with property owners to discuss and compensate for any damage caused by construction, including damage to crops and fences.

Will my trees be trimmed or removed?
Any tree located within 金沙娱乐 right-of-way limits that will interfere with construction or operations will need to be removed. Any trees with branches overhanging 金沙娱乐 right-of-way limits will need to be side trimmed. All work performed will be overseen by a trained tree professional.